Do not click Batch congurations shown in the following gure to send the array
startup/shutdown command, because this will aect the phase sequence check.
Figure 4-14 Completing the conguration
----End
4.2.4 Checking the Phase Sequence
Phase sequence check is to conrm whether the phase sequence of AC power
cables of the PCS is consistent with that of the transformer and power grid. If the
phase sequences are inconsistent, o-grid operation may be abnormal.
Step 1 Log in to the SmartLogger WebUI, choose Overview > Active Alarm, and check
whether the PCS reports a Reverse Phase Sequence on AC Side alarm.
Step 2 If the PCS reports a Reverse Phase Sequence on AC Side alarm:
1. Shut down the PCS, and turn o the power switches on the AC and DC sides
of the PCS.
2. Correct the wiring sequence of the PCS AC power cables. If the PCS AC power
cable is a multi-core cable, you are advised to exchange L1 and L3 shown in
the following gure to meet the stripping length requirement.
Commercial and Industrial Microgrid Energy Storage
Solution
Quick Guide (With Third-Party Microgrid Central
Controller) 4 System Power-On and Commissioning