NO TE
Cables to COM-1 on Pack1 and COM-2 on Pack12 are reserved before delivery. After
connecting the cables to the battery packs, bind the cables inside the cabinet. Connect
the other ends of the cables after installing the rack controller.
Other COM port cables are delivered with the product.
The cable sequence is as follows: Pack1-2-3-4-5-6-7-8-9-10-11-12.
The cable between Pack5 and Pack6 is 04097837-08, the cable between Pack10 and
Pack11 is 04097837-09, and the other cables are 04097837-06.
Figure 8-4 Connecting cables to the COM ports on the battery packs
Step 4 Close the terminal covers of the battery packs.
----End
LUNA2000-200KWH-2H1 Smart String ESS
User Manual 8 Installing Cables