● Ensure that the power circuit breaker is OFF before installing batteries.
● When installing batteries, do not place installation tools, metal parts, or
sundries on the batteries. After the installation is complete, clean up the
objects on the batteries and the surrounding area.
● When moving batteries, do not remove protective components such as
protective covers or waterproof caps from battery terminals.
● Do not move or operate under the forklift tynes.
● You can operate the battery pack installation kit only after the forklift
stops moving.
● Slowly push or move battery packs to prevent damage and collision.
● To prevent battery packs from falling o, start the pallet truck or forklift
after conrming that battery packs are securely bound.
● Before installation, ensure that battery packs are stored indoors and that
other storage requirements specied in the user manual are met.
● Before installation, check the status of the battery packs. Do not use the
battery packs if the packing cases are exposed to rain, damaged, or
deformed, or if the battery packs leak or fall.
● Install batteries within 24 hours after unpacking. If the batteries cannot be
installed in time, put them in the original packaging and place them in a
dry indoor environment without corrosive gases. Power on the ESS within
24 hours after installation. The process from unpacking batteries to
powering on the system must be completed within 72 hours. During
routine maintenance, ensure that the power-o time does not exceed 24
hours.
● Do not install battery packs on rainy, snowy, or foggy days. Otherwise, the
battery packs may be corroded by moisture or rain.
Procedure
Step 1 Remove the column in the middle.
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 7 Installation