7.4.3 Installing the Smart Rack Controller
Prerequisites
Unpack and check the rack controller delivered to the site to ensure that it is
intact.
Procedure
Step 1 Remove the decorative cover and maintenance compartment cover from the rack
controller.
Figure 7-24 Removing covers
Step 2 Install short-circuiting copper bars that are delivered with the product.
NO TE
When installing a nut, manually insert the nut into the screw plate, and then use a
socket wrench to completely secure the nut in place. This prevents the screw thread
from being stuck or stripped due to the deviation of the nut position.
Preinstall nuts according to the recommended torque of 21 N·m.
Verify the torque of the installed nuts using a torque socket wrench set to 21 N·m.
Mark the nuts whose torque has been veried using a marker.
Figure 7-25 Installing short-circuiting copper bars (200 kWh model)
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 7 Installation
Issue 10 (2023-11-07) Copyright © Huawei Digital Power Technologies Co., Ltd. 97

Table of Contents

Related product manuals