Step 4 Close the terminal covers of the battery packs.
----End
8.4 Installing Rack Controller Cables
Step 1 Remove the decorative cover and maintenance compartment cover from the rack
controller.
Figure 8-8 Removing covers
Step 2 Connect the preinstalled cables to the BAT/BUS ports. Magnetic rings are delivered
with the product.
● The black magnetic ring is installed on the left side of the rack controller, and
the green magnetic ring is installed on the right side of the rack controller.
● Do not remove the cover from an unused pagoda connector.
Figure 8-9 Connecting cables (200 kWh model)
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 8 Installing Cables
Issue 10 (2023-11-07) Copyright © Huawei Digital Power Technologies Co., Ltd. 115