No. Check Item Expected Result
6 Foreign object Foreign objects such as tools and
remaining materials are cleared.
7 Bae plate for the
power distribution
area
The bae plate in the power distribution
area is free from cracks, dents, scratches,
openings, and looseness.
8 SPD The SPD indicator is green.
9 Subcomponent
(CMU, adapter, and
rack mounted re
extinguishing
system)
All components are intact.
10 Cabinet grounding The ground conductor is reliably
connected to the ground terminal board
or copper bar of the cabinet.
9.2 Installing a PSU
Prerequisites
The PSU is secured inside the ESS during transportation and installed onsite.
● If a PSU is damaged, contact the local oce.
● Do not put your hands into the PSU slot to avoid electric shock.
● In an outdoor scenario, you are advised to power on the PSU within 24 hours
after unpacking. If the PSU cannot be powered on in time, place it in a dry
indoor environment without corrosive gas.
Procedure
Step 1 Push the locking latch leftwards.
Step 2 Pull out the handle.
Step 3 Gently push the PSU into its slot along the guide rails.
Step 4 Push the handle upwards.
Step 5 Push the locking latch rightwards to lock the handle.
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 9 Powering On the ESS
Issue 10 (2023-11-07) Copyright © Huawei Digital Power Technologies Co., Ltd. 129