Procedure
Figure 9-2 Positions of switches
(1) 48 V DC power distribution
switches
(2) AC main switch (1FCB) (3) 12 V adapter switch
(1FCB1)
(4) PSU switch (1FCB2) (5) UPS switch (5FCB) (6) 220 V maintenance socket
switch (1FB1)
(7) DC switch (1Q1, on the
battery rack side)
(8) DC switch (1Q2, on the
Smart PCS DC side)
-
Step 1 Turn on the switch between the AC side of the ESS and the power grid.
Step 2 Turn on the DC switch 1Q1. (As shown by 7 in Figure 9-2)
Step 3 Use a multimeter to check whether the AC voltage is within the allowed range
(220 V±10%). (As shown by 2 in Figure 9-2)
Step 4 (Optional) Turn on the UPS cable inlet switch 5FCB (as shown by 5 in Figure 9-2).
Step 5 Turn on the AC main switch 1FCB. (As shown by 2 in Figure 9-2)
Step 6 Turn on all switches in the power distribution system of the ESS.
1. Turn on the 12 V adapter switch 1FCB1. (As shown by 3 in Figure 9-2)
2. Turn on the PSU switch 1FCB2. (As shown by 4 in Figure 9-2)
3. (Optional) Turn on the 220 V maintenance socket switch 1FB1. (As shown by
6 in Figure 9-2)
4. On the embedded power subrack (SK1), turn on the DC/DC switch 2FCB1, DC
light power switch 2FCB2, TCUE power switch 2FCB3, fan 1 switch 2FCB6, fan