8 Power-On Commissioning
Context
● The power-on commissioning process requires as least two qualied
electricians, one responsible for operations and the other for monitoring.
● Cautions and warnings must be properly placed onsite.
● Powering o the combiner cabinet disconnects the power supply to the
downstream devices. Exercise caution with this operation when the combiner
cabinet is supplying power to a working system.
Procedure
Step 1 Perform the insulation check only after the upstream and downstream circuit
breakers of the combiner cabinet are powered o.
1. Disconnect the SPD fuses FU9 and FU10 in the combiner cabinet, connect the
PSU fuses FU11 and FU12, and turn on all output disconnectors.
2. Use a multimeter to check that the insulation resistance between the positive
and negative terminals of the SPD, and between the positive and negative
terminals and PE is at least 0.5 megohm.
Figure 8-1 SPD voltage measurement position
3. After the check is complete, switch o all output disconnectors in the
combiner cabinet.
PDU8000 DC Combiner Cabinet
Quick Guide 8 Power-On Commissioning
Issue 02 (2022-08-10) Copyright © Huawei Digital Power Technologies Co., Ltd. 30