Procedure
Step 1 Determine a position for installing the mounting brackets.
l If the RRU is installed on a tower, determine a position for installing the mounting brackets
according to the instructions in 3.5.1 Clearance for a Single RRU.
l If the RRU is installed on the ground, determine a position for installing the mounting
brackets according to Figure 7-3.
Figure 7-3 Distance between the mounting brackets and the ground
NOTE
As shown in the figure above, it is recommended that the mounting kits be installed at a position
1200 mm (47.24 in.) to 1600 mm (59.06 in.) high above the ground. If the space is insufficient, only
the 3.5 Installation Clearance Requirements of an RRU needs to be provided.
Step 2 Install the RRU mounting brackets, as shown in Figure 7-4.
Figure 7-4 Installing the RRU mounting brackets
7 Installing the RRU
Issue () Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.