STS-(3000K, 6000K)-H1 Smart Transformer
Station (Spain, Eiffage Turroneros)
Installation Guide
Issue
02
Date
2020-02-21
HUAWEI TECHNOLOGIES CO., LTD.

Table of Contents

Question and Answer IconNeed help?

Do you have a question about the Huawei STS-6000K-H1 and is the answer not in the manual?

Huawei STS-6000K-H1 Specifications

General IconGeneral
BrandHuawei
ModelSTS-6000K-H1
CategoryTransformer
LanguageEnglish

Summary

Safety Precautions

Electrical Safety

Grounding Requirements

Install ground cable first, remove last. Do not damage ground conductor. Operate only with proper grounding.

Electrical Connections Requirements

Ensure connections comply with standards. Obtain utility approval. Use insulated tools for high-voltage operations.

Site and Mechanical Safety

Maintenance and Replacement

Maintenance Safety Notice

Wait 10 mins after shutdown. Turn off LV/HV switches. Attach warning labels. Use proper tools. Power off before maintenance.

Equipment Installation

Site Selection Criteria

Location criteria: not low-lying, well-ventilated, away from interference, facilities, pollution sources.

Foundation Construction Requirements

Concrete pad, trench, ground grid, ground copper bar, ground resistance requirements.

Hoisting Operations

Hoisting Parameters and Precautions

Table of container weights and rope lengths. Precautions before and during hoisting.

Hoisting Procedure

Steps to determine position, measure support points, and hoist the container.

Hoisting Equipment Steps

Steps to remove rainproof cloth, customs lock, and sealing plate.

Verification and Securing

STS Overall Check

Overall Check Acceptance Criteria

Checks for foreign matter, component intactness, SF6 barometer, switch ops, LV cabinet, oil level.

Operating Components

STS Insulation Tests

Insulation Test Scope and Timing

Covers MV/LV sides, ring main unit. Perform tests before connecting incoming cables.

Connecting Cables

Cable Connection Precautions

DANGER: ensure switches off. WARNING: device damage, qualified personnel, PPE, cable slack.

PE and AC Input Cable Connections

PE Cable Grounding Requirements

Grounding must comply with local electrical safety regulations.

PE Cable Connection Procedure

Steps to connect PE cable to chassis shell or main ground bar in LV room.

AC Input Cable Terminal Requirements

Requirements for copper/aluminum cables and terminals (OT/DT) to prevent corrosion.

AC Cable Connection Details

OT/DT Terminal Connection Examples

Illustrates correct OT/DT terminal connections for different cable types.

AC Input Power Cable Connection Steps

Detailed steps for connecting AC input power cable, including torque and sealing.

Lightning Arrester Installation

Lightning Arrester Installation Warning

Install after insulation test. Requires sunny, dust-free, wind-free environment. Clean surfaces.

Lightning Arrester Installation Position

Shows the position for installing the lightning arrester in cabinet G2 of the ring main unit.

Lightning Arrester Installation Steps

Steps to adjust support height and install the lightning arrester.

Securing Lightning Arrester Support

Illustrates securing the lightning arrester support with torque specifications.

AC Output Cable and SACU Connections

AC Output Cable Connection Notice

Notes on interlocking doors, grounding switches, insulation plugs, routing, and foundation height.

AC Output Power Cable Connection Procedure

Steps to cut cable inlet and prepare terminals for AC output power cable.

AC Output Cable Connection Diagrams

Illustrates connecting AC output cables for single and cascaded STSs.

Cable Access and Securing

Steps to fill insulation layer, secure cables, seal holes, and close doors.

Verifying Installation and Connections

Installation and Cable Connection Verification Criteria

Checks for correct installation, switch status, cable connections, screw tightness, sealing, and environment.