Figure 4-13 Lifting positions
Procedure
Step 1 Lift the solar inverter from the packing case and move it to the installation
position.
Figure 4-14 Taking out the solar inverter
Step 2 (Optional) Install screws for locking DC switches.
SUN2000-(100KTL, 110KTL, 125KTL) Series
User Manual 4 Installation
Issue 07 (2020-09-15) Copyright © Huawei Technologies Co., Ltd. 35