PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
2 Installation Preparations
Copyright © Huawei Technologies Co., Ltd.
Ensure that components do not collide with doors, walls, or shelves.
Wear clean gloves. Do not touch components with bare hands or wet or dirty gloves.
Procedure
Step 1 Check the total number of goods against the packing list attached to each packing case.
If...
Then...
The total number of goods is consistent with
that on the packing list.
Go to Step 2.
The total number of goods is inconsistent
with that on the packing list.
Find the cause and contact the local Huawei
office.
Step 2 Check each packing case.
If...
Then...
The packing case is intact.
Go to Step 3.
The packing case is severely damaged or
water intrudes into the packing case.
Find the cause and contact the local Huawei
office.
Step 3 Check the number and types of devices in each packing case against the packing list.
If...
Then...
The number and types of devices are
consistent with that on the packing list.
Sign on the Packing List with the customer.
Any device is missing, damaged, or of a
wrong type.
Contact the local Huawei office.
To protect devices and facilitate future problem diagnosis, store unpacked devices and
packing materials indoors. Take photos of the storage site, any rusty or corroded devices, and
the packing cases and materials. Keep the photos for future reference.
----End
2.5 Requirements for Laying Out Cables
Lay out cables according to the following requirements to avoid signal interference.
If some of the cables described below do not need to be installed onsite, ignore the requirements for