Please complete & Sign this form and fax to HYDROTEC to arrange commissioning of your HydroWELL
®
Water
Disinfection Unit on FAX: 01494 796 049 or Email: services@hydrotec.co.uk
Name
Site Contact
Company
Company
Address
Site Address
Full Postcode
Full Postcode
Tel
Site Tel
Fax
Installation Area
Tick to confirm:
The HydroWELL has been installed as per our Installation Instructions.
All parts are on site as per packing checklist.
The control box has been secured to the wall.
Electrical supply (fused spur outlet 240V AC 50Hz 5AMP) within 1.5 metres of control box has been
provided and connected. (DO NOT TURN THE POWER ON).
Isolation valves have been installed either side of the UV vessel.
Compact models only: The UV vessel has been installed in horizontal pipework with the reactor vessel
vertically (drain cock down).
Standard models only: The UV vessel has been installed in vertical pipework with the reactor vessel
horizontally (drain cock down).
Select models only: The UV vessel has been installed in horizontal pipework with the reactor vessel
horizontally (drain cock down).
There is a minimum of 500mm free servicing clearance measured from the end of the lamp head(s).
The UV vessel is plumbed in and water to inlet valve is provided.
The building has been cleaned / sterilised to BS8558 standard.
On-site parking will be available.
By signing this form we agree to the following: Should any of the above not have been carried out at the
time of the agreed visit; a further inspection will be required prior to a Commissioning Certificate being
issued. This will be carried out upon the issue of a Purchase Order for £500.00. Less than 48 hours
cancellation notice will also incur a £350.00 charge.
Please do not hesitate to call us should you be having difficulties with the completion of this form.
Required commissioning date ___ / ___ / ____. Commissioning is normally carried out within
15 working days.
Signed……………………......... Print Name……..……………………………………..Date…………………......
For Office Use Only:
Job No:
Model:
Serial No:
No of
Units:
Ship Date:
Remarks:
Hydrotec Engineers
Comments: