EasyManuals Logo

IEC Modular Hi-Rise Series User Manual

IEC Modular Hi-Rise Series
28 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #16 background imageLoading...
Page #16 background image
or gain. All of the risers including the riser stubouts should
be properly covered with insulation. Internally mounted
chilled water piping and valves are located over the drain
pan and need not be insulated.
Any reproong requirements where risers or piping
penetrate oors or walls are the responsibility of the
installer. This work should be done only after all pressure
testing is completed. The reproong method used must
accommodate pipe expansion and contraction and the
piping must be protected from abrasion and chemical attack.
The pipe insulation also must be maintained to prevent
sweating and must be protected from wear or erosion at the
joint between the insulation and the reproong material.
When no risers are ordered for the Mega Modular unit, it is
the responsibility of the installer to make sure that a eld
supplied isolation ball valve is installed between each supply
and return piping connection to the unit. Flare ttings are
factory provided to allow connection between the ball valves
and the hoses.
Variations in oor-to-oor dimensions may require eld work
such as cutting o or extending the risers. This operation is
the responsibility of the installer. The riser joint ller material
must be selected to withstand the total operating pressure
(both static and pumping head) to which the system will be
subjected. Low temperature lead alloy solders such as “50/50”
and “60/40” are normally not suitable.
Chilled water and hot water risers should never be piped
to drain down into the condensate riser. Extensive water
damage can occur due to drain overow. Drain chilled and
hot water risers to a remote location away from the unit such
as sink, room and oor drains.
All installations should be made in compliance with all
governing codes and ordinances. Compliance with all
codes is the responsibility of the installing contractor.
Unit Knockout Locations (Typical)
Side Supply Air
Knockout
(1 per side)
SIDE VIEW
Mega Mod
Cabinet
Optional
Supply
Plenum
Figure 21
Top Supply
Air Knockout
TOP VIEW
Electrical
Knockouts
Figure 22
Supply Air Installation
Knockout Tab
(10 places)
Duct Break
(4 places)
Knockout Tab
Trim Line
Figure 23
16
16
Modular Hi-Rise Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IEC Modular Hi-Rise Series and is the answer not in the manual?

IEC Modular Hi-Rise Series Specifications

General IconGeneral
BrandIEC
ModelModular Hi-Rise Series
CategoryFan
LanguageEnglish