SECTION 5 - SYSTEM COMMISSIONING
JOHNSON CONTROLS
131
FORM 160.72-O1 (810)
5
5
JOHNSON CONTROLS
3
FORM 160.72-CL1 (810)
With reference to the terms of the above contract, we are requesting the presence of your Authorized Representative at the job site on
Month
_______ /
Day
________ /
Year
_______ to start the system and instruct operating personnel ________________________
We understand that the services of the YORK/Johnson Controls Authorized Representative will be furnished in accordance with the contract for a
period of time of not more than _____ consecutive normal working hours, and we agree that a charge of _______ per diem plus travel expenses
will be made to Johnson Controls if services are required for longer than ______ consecutive normal hours or if repeated calls are required,
through no fault of YORK/Johnson Controls.
Names
HAVE
CONTACT
Signed:
Title:
BINARY OUTPUTS
DEVICE DESCRIPTION PASS
FCV-104 Auxiliary Cooling Water Solenoid Valve
FCV-114 Interstage Liquid Injection Solenoid Valve
FCV-120 Oil Eductor Solenoid Valve
HTR-120A/B Oil Separator Heaters
HTR-143A/B Compressor Oil Sump Heaters
HTR-160A/B Motor Space/Motor Exciter Heaters
M1 Compressor Motor Start/Stop
M2 Compressor Auxiliary Oil Pump Start/Stop
M3 Gear Auxiliary Oil Pump Start/Stop
PCV-100A Compressor Pre-Rotation Vanes Air Dump Solenoid Valve
PCV-100C Hot Gas Bypass Valve Air Dump Solenoid Valve
PCV-143 Compressor Sump Vent Solenoid Valve