EasyManua.ls Logo

Johnson Controls YORK Tempo YLAA0101HE - Section 6 - Commissioning; Preparation - Power off; Inspection; Refrigerant Charge

Johnson Controls YORK Tempo YLAA0101HE
192 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
FORM 150.72-NM1 (1020)
119
JOHNSON CONTROLS
6
Commissioning of this unit should only
be carried out by Johnson Controls
Authorized personnel.
Commissioning personnel should be thoroughly familiar
with the information contained in this literature, in
addition to this section.
Perform the commissioning using the detailed checks
outlined in the “Equipment Pre-Startup and Startup
Check List” (Page 120) as the commissioning procedure
is carried out.
PREPARATION POWER OFF
The following basic checks should be made with the
customer power to the unit switched OFF.
Inspection
Inspect unit for installation damage. If found, take action
and/or repair as appropriate.
Refrigerant Charge
Packaged units are normally shipped as standard with a
full refrigerant operating charge. Check that refrigerant
pressure is present in both systems and that no leaks are
apparent. If no pressure is present, a leak test must be
undertaken, the leak(s) located and repaired. Remote
systems and units are supplied with a nitrogen holding
charge. These systems must be evacuated with a suitable
vacuum pump/recovery unit as appropriate to below
500 microns.
Do not liquid charge with static water in the cooler.
Care must also be taken to liquid charge slowly to avoid
excessive thermal stress at the charging point. Once the
vacuum is broken, charge into the condenser coils with
the full operating charge as given in the Technical Data
Section.
Service and Oil Line Valves
Open each compressor suction, economizer, and
discharge service valve. If valves are of the back-seat
type, open them fully (counterclockwise) then close one
turn of the stem to ensure operating pressure is fed to
pressure transducers. Open the liquid line service valve
and oil return line ball valve fully in each system.
Compressor Oil
To add oil to a circuit – connect a YORK hand oil pump
(Part No. 470-10654-000) to the 1/4” oil charging
connection on the compressors with a length of clean
hose or copper line, but do not tighten the are nut.
Using clean oil of the correct type (“V” oil), pump oil
until all air has been purged from the hose then tighten
the nut. Stroke the oil pump to add oil to the oil system.
Approximately 1.8 to 2.3 gallons is present in the each
refrigerant system. Oil levels in the oil equalizing line
sight glass should be between the bottom and the middle
of the sight glass with the system o. High oil levels
may cause excessive oil carryover in the system. High
oil concentration in the system may cause nuisance trips
resulting from incorrect readings on the level sensor
and temperature sensors. Temperature sensor errors
may result in poor liquid control and resultant liquid
overfeed and subsequent damage to the compressor.
While running, a visible sign of oil splashing in the
sight glass is normal.
Fans
Check that all fans are free to rotate and are not damaged.
Ensure blades are at the same height when rotated.
Ensure fan guards are securely xed.
Isolation / Protection
Verify all sources of electrical supply to the unit are taken
from a single point of isolation. Check that the maximum
recommended fuse sizes given in the Technical Data
Section has not been exceeded.
Control Panel
Check the panel to see that it is free of foreign materials
(wire, metal chips, etc.) and clean out if required.
Power Connections
Check that the customer power cables are connected
correctly to the terminal blocks or optional circuit
breaker. Ensure that connections of power cables within
the panels to the circuit breaker or terminal blocks are
tight.
Grounding
Verify that the unit’s protective ground terminal(s) are
properly connected to a suitable grounding point. Ensure
that all unit internal ground connections are tight.
Supply Voltage
Verify that the site voltage supply corresponds to the
unit requirement and is within the limits given in the
Technical Data Section.
SECTION 6 – COMMISSIONING

Table of Contents

Related product manuals