1266554-A02-A 14
9. After completing the wiring work, adjust power
input and lock the junction box cover.
10. Ensure the in-wall tank water outlet hose
connection is tightened and does not leak.
11. Turn power switch to ON and open water inlet
valve
12. Apply silicone sealant around the back edge of the pan
to ensure a clean adhesion to the wall.
Install the left and right side panels.
1. Slide water splash plate into Slot A and B in square cover.
NOTE: After the splash plate is installed, the locators should be
under the surface.
Locators