54
9. Operating Procedures For Single Systems
9.1. Preparations
UPS is shipped with 3pcs of battery fast fuses in a plastic package attached to the front side of UPS.
After all connections are completed as described in KEOR T EVO Installation Manual, the battery fuses
must be placed as shown below. The fuses’ indicators should be placed at top. Use only the fuses
delivered with the UPS.
Figure.9.1-1
KEOR T EVO 10-15-20KVA