Wall mounting
Wiring according to EMC requirements
3
EDK82MV371 DE/EN/FR 6.0
87
L
Conditions for trouble−free operation:
l Except for the mains cable, use shielded cables only.
l The shield must be carefully connected to PE.
l Separate control and mains cables from motor cable!
l Connect motor and mains PE conductors to separate PE terminals.
Fig. 15
8200mot100
Fig. 16
A
B
F
G
D
C
I
H
8200mot169
X1
X2
Shield connection
1. Prepare cable
2. Insert the cable tie
3. Lay cable into the
cable tie and tighten
it. The shield must be
tightly connected to
the shield sheet.
Mains cable L1, N, PE or L1, L2, PE
PE connection − mains cable
Shield connection − motor cable: fix the shield with cable binder to the sheet
Shielded motor cable (use low−capacity motor cables)
PE connection − motor cable
Shield connection − control cable (fix the shield with cable binder to the sheet)
Shielded control cable
Function module
X1 Terminal strip − mains connection
X2 Terminal strip − motor connection
PES HF screen termination by PE connection with a surface as large as possible