1
2
3
4
5
6
7
© 2014 MIMAKI ENGINEERING CO.,LTD. 7. P.1R.1.0
INSTALLATION GUIDE > Outputting Plots
Model
CJV300
Issue
2014.09.01
Revised F/W ver.
1.30
Remark
1.0
7. Outputting Plots
List of work procedures
Work operation Description Refer to
1
Initial Ink Fill Execute the initial ink fill 7.1 (p.2)
2
Test Print Check that there are no plotting problems, such as missing nozzles or bent paths 7.2 (p.9)
3
Cleaning the Heads Carry out if a drawing failure occurs in the test print. 7.3 (p.11)
4
Dot Position Adjustment
(Service mode)
Execute dot position adjustment if misalignments occur during bidirectional plotting 7.4 (p.12)
5
Dot Position Adjustment
(User menu)