5.4 Testing the CC-Link IE Controller Network Module
This section describes the tests of the CC-Link IE Controller Network module.
Before starting up the system, the test is to be performed to check the CC-Link IE Controller Network module and
cables.
Perform each test according to the following.
Connect wires to the external power supply terminal
block of the CC-Link IE controller network module.
Turn OFF the external power (24V DC).
1)
Turn ON the external power (24V DC).
Check the external power voltage of the CC-Link IE
controller network module is within the specified range.
Mount the CPU module, power supply module,
CC-Link IE controller network module, etc. to the base unit.
Start
Is it CC-Link IE controller
network module with external
power supply function?
No
Yes
ON
OFF
Is the EXT.PW LED on
the CC-Link IE controller network
module ON?
The CC-Link IE controller network module hardware
may be faulty. Please consult your local Mitsubishi
representative.
Turning OFF external power (24V DC)
Wiring
Applying external power (24V DC)
Before applying external power (24V DC)
Mounting modules