9 - 99
MELSEC-Q
9 MAJOR POSITIONING CONTROL
Operation timing and processing time during speed-position switching
control (ABS mode)
Positioning start
signal [Y10,Y11,Y12,Y13]
BUSY signal
M code ON signal
[X4,X5,X6,X7] (WITH mode)
Standby Speed control
Start complete signal
Output pulse to external source
(PULSE)
Positioning operation
Positioning complete signal
M code ON signal (AFTER mode)
t1
t2
t3
t4
t5
t2
t7
Position control
Speed
control
Position
control
External speed-position
switching command
t6
Speed control carried out until speed-position switching
signal turns ON
Md.26
Axis operation status
OPR complete flag
Md.31 Status: b4
Cd.7
M code OFF request
Cd.7 M code OFF request
Standby
[XC,XD,XE,XF]
[X10,X11,X12,X13]
[X14,X15,X16,X17]
[X4,X5,X6,X7]
Fig. 9.17 Operation timing and processing time during speed-position switching control (ABS mode)
Normal timing time
Model t1 t2 t3 t4 t5 t6 t7
QD75P N/QD75D N 0.2 to 1.1ms 0 to 0.9ms 0 to 0.9ms 0.4 to 1.3ms 0 to 0.9ms 1.0ms
QD75P /QD75D 1.1ms 0 to 1.8ms 0 to 1.8ms 2.7 to 4.4ms 0 to 1.8ms 1.0ms
Follows
parameters
The t1 timing time could be delayed by the operation state of other axes.