7.9 Information
BU 0750 GB Technical design subject to change 121
Setting value / Description / Note
Time for which voltage has been applied to the inverter making it ready for operation.
Time for which the inverter has been in an enabled state supplying current at its output.
Displays the current output frequency.
Displays the current motor speed as calculated by the inverter.
P718 ... - 01
... - 02
... - 03
Displays the frequency which has been defined as the setpoint (see also 10.1 Setpoint process-
ing)
... - 01 = present set frequency from the source of the setpoints
... - 02 = present set frequency after being processed in the inverter
... - 03 = present set frequency after the frequency ramp
Displays the output current being supplied the moment the inquiry is made.
Displays the torque-generating output current calculated the moment the inquiry is made. Cal-
culation will be based on the motor data entered in parameters P201 …P209.
-500.0 ... 500.0 A negative values = regenerative operation, positive values = power made
available directly by the motor
Displays the field current calculated the moment the inquiry is made. Calculation will be based
on the motor data entered in parameters P201 …P209.
Displays the voltage currently being supplied at the inverter output.
Displays the field current component determined the moment the inquiry is made.
Displays the torque voltage component determined the moment the inquiry is made.
Displays the popwer factor of the drive calculated the moment the inquiry is made.
Displays the apparent power calculated the moment the inquiry is made. Calculation will be
based on the motor data entered in parameters P201 …P209.
Displays the effective power calculated the moment the inquiry is made. Calculation will be
based on the motor data entered in parameters P201 …P209.