14 | nVent.com/ERICO
Figure : Cable pre-termination and drum locations
Figure : Incorrect and correct cable hoisting methods
Downconductor
terminated end
hauled from the
ground to the top
of the structure
Downconductor
preterminated end on
the inside of the drum
DO NOT cut plastic cover over
terminated downconductor
as this may damage the
termination inside
Downconductor
un-terminated
end lowered to
the ground
Downconductor preterminated
end on the outside of drum
INCORRECT
CORRECT