Before You Begin
Use this guide to install and begin setting up your Palo Alto Networks
®
PA-220R next-generation firewall. Refer to the PA-220R
Next-Gen Firewall Hardware Reference at https://docs.paloaltonetworks.com/hardware for safety information, specifications,
and more detailed procedures for installing your firewall.
Verify that the installation site has a DC power source.
Unpack the equipment and verify that you received the following items:
Install the Firewall
There are four ways to install the PA-220R firewall:
On a flat surface
On a DIN rail
On a wall
In a 19-inch equipment rack
Install on a Flat Surface
Attach the rubber pads to the recessed circles on the bottom of the firewall (Figure 1) and place the firewall securely on a stable
flat surface (right-side up).
Install on a DIN Rail
You can attach the DIN bracket to either the back or to the bottom surface of the firewall. Choose the option that best fits the
installation site.
1 Attach a 35mm DIN rail (not included) to the wall where you will install the firewall.
2 Attach the DIN bracket to the back (Figure 2) or bottom surface (Figure 4)of the firewall (use the DIN bracket captive screws). Ensure that
the spring-loaded clips on the DIN bracket are oriented so that they will grasp the bottom of the DIN rail.
3 Engage the bottom of the DIN bracket (with spring-loaded clips) with the bottom part of the DIN rail. Push the firewall and bracket upward
to fully compress the spring-loaded clips against the rail and then pivot the firewall toward the wall so that the top clips on the bracket will
grasp the top of the rail as you carefully lower the firewall to decompress the clips and secure the firewall on the DIN rail (Figure 3 or Figure
5).
Qty Description
1 PA-220R next-generation firewall.
1 Standard Type-A USB to micro USB console cable.
1 DB-9 female to RJ-45 male console cable.
1 Shielded RJ-45 CAT6 Ethernet cable for management (MGT) port access.
1 DC terminal block.
4 Rubber pads for a desktop installation.
1 DIN bracket for a DIN rail installation.
1 End User License Agreement (EULA).
1 China Restriction of Hazardous Substances (RoHS) declaration.
DIN Bracket
Spring-loaded
DIN Bracket Clips
Capve Screw
Capve Screw
Capve Screw
Spring-loaded
DIN Bracket Clips
DIN Bracket
Capve Screw
DIN Rail
Spring-loaded
DIN Bracket Clips
Wall
DIN Rail
Spring-loaded
DIN Bracket Clips
Wall
Figure 2
Figure 4
Figure 3
Figure 5
Figure 1
PA-220R
Quick Start Guide
1
2
The PA-220R firewall ships with rubber pads (to install the firewall on a flat surface) and a DIN rail bracket (to install the firewall on a DIN
rail). The wall-mount kit and 19-inch equipment-rack kit are optional and purchased separately—refer to the PA-220R Next-Gen Firewall
Hardware Reference for the wall-mount and rack-kit installation procedures.
docs.paloaltonetworks.com
Page 1 of 2

Other manuals for PaloAlto Networks PA-220R

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the PaloAlto Networks PA-220R and is the answer not in the manual?

PaloAlto Networks PA-220R Specifications

General IconGeneral
ModelPA-220R
Form FactorDesktop
Firewall Throughput (HTTP/appmix)500 Mbps
Firewall Throughput1 Gbps
IPsec VPN Throughput250 Mbps
VPN Throughput250 Mbps
Maximum Sessions64, 000
New Sessions Per Second5, 000
Power SupplyInternal
Input Voltage100-240 VAC
Humidity10% to 90% non-condensing
Weight3.5 lbs
Operating Temperature32°F to 104°F (0°C to 40°C)
Storage Temperature-40°F to 158°F