ITS Power over Ethernet Unit Test and Inspection Procedures
IntelliVue Telemetry System Infrastructure Installation and Service Guide 5-5
ITS Power over Ethernet Unit Test and Inspection Procedures
Table 5-7 lists which tests you must perform when performing service events on
IntelliVue Telemetry System PoE Unit.
Table 5-7: ITS PoE Unit Test and Inspection Requirements
When Performing this
Service Event...
Complete These Required Test(s)
Installation Visual, Power On
Preventive Maintenance N/A
Any component repair or replacement Power On
Hardware Upgrade N/A
Software Upgrade N/A
All other Service Events Visual, Power On
Table 5-8: ITS PoE Unit Test and Inspection Matrix
Test Block
Name
Test or Inspection to Perform Expected Results
Information to
Record on
Service Record
PoE Unit V
isual Inspect all system components for
obvious damage. Visually inspect all
system components, cables, and
connectors. Check for signs of abrasion,
wear, or other damage.
No visible damage V:P or V:F
where:
P = Pass
F = Fail
PoE Unit
Power On
With power connected to each active
Network device, observe that all lights
visible on the front panel are in proper
status and that no error conditions are
shown.
Verify that the AC LED on front panel is
solid GREEN. Verify that the Link LED is
lit GREEN for each connected cable.
Devices power up
into expected
status; no error
indications are
shown.
PO:P or PO:F
where:
P = Pass
F = Fail
PoE Unit
P
erformance
No performance check is required. P:NA
where:
NA=Not
Applicable
PoE Unit
R
evision Check
No revision check is required. RC:NA
where:
NA=Not
Applicable
Sync Unit
Safety
No safety test is required S:NA
where:
NA=Not
Applicable