22
Chapter 4 Commissioning
Firstly confirm that AC input power supply voltage shall be within inverter
rated input voltage range before connecting power supply to the inverter.
Connect AC power supply to the R, S and T input terminals of the inverter,
or solar power to the R, T input terminals of the inverter.
Select the appropriate operation control method.
Commissioning
Select control manner
(Set F0.00)
F0.00=?
Select command source
(Set F0.11)
Select suitable frequency source
(Set F0.03)
Select motor start-up mode
(Set F3.00)
Select appropriate ac/deceleration time
(Set F0.13、F0.14)
Select motor stop mode
(Set F3.07)
Start motor to run,observe the
phenomenon,if abnormal,please
refer to the troubleshooting
Achieve the required control effect?
Commissioning
Correctly motor parameters
(Set b0.00 b0 . 05)
Select appropriate ac/deceleration time
(Set F0.13、F0.14)
Motor parameter self-learning
(Set b0.27)
2:V/F control
0:Vector control W/O PG
YES
NO