BES X installation manual Scoring network
P/N: 400288005; Rev: L, 09/21 55
T.20.104 – 4HD/5HD-HUB installed on XLi pinspotters with low ceiling safety kit
A
Solid homerun cable
from Conqueror roP
server
4 /5HDHD
HUB
Patch network
cables to other
4 - unitsHD HUB
or SLAVE
Scoring Network
switches
MAIN Scoring
NET switch
A
B
B
Patch network
cable from the main
Scoring Network
switch
4 /5HDHD
HUB
With Xli pinspotters with the low ceiling safety kit, always install the 4HD/5HD-HUB unit and all other
devices to the panel located between each pair of pinspotters, as shown in the details A and B.
The MAIN Scoring NET switch has to be installed in the middle of the Scoring Network. For example, in a
8 lanes installation the MAIN Scoring NET switch has to be installed between the lane 4 and the lane 5.
Do NOT run any scoring system cable in the pinspotter conduits for any reason.
Keep the scoring system cables far away from any power cable.