INTRODUCTION
INSTALLATION OVERVIEW
The recommended process for installing the Hawkeye® 2 nozzle control system is as follows:
1. Confirm Hawkeye® 2 kit contents. See “Kit Contents” on page 8.
2. Replace existing strainer with an 80 mesh (or finer) strainer.
3. Remove spray tips and flush each section individually for a minimum of 20 seconds to thoroughly flush the
boom.
4. Mount Hawkeye® 2 nozzle control valves.
5. Route and connect the inner, mid, and outer boom cables (as applicable).
6. Mount the RCM - Sprayer.
7. Route and connect chassis and RCM - Sprayer cables.
8. Review the Post-Installation Notes for machine configuration tips.
REQUIRED COMPONENTS
The following components must be installed with the Hawkeye® 2 nozzle control system:
Updated software on field computers or control monitors
PWM pump control valve
Raven compatible flow meter
Raven compatible pressure transducer
80 (or finer) mesh strainer
NOTE: Air induction style spray tips should not be used with the Hawkeye® 2 nozzle control system. A fan or
cone style spray tip is required for the Hawkeye® 2 system to operate properly.
TOOLS AND MATERIALS NEEDED
The following tools are recommended for completing the installation:
SAE and metric sized wrenches and tools
Drill bit set and drill
•Corrosion X HD
Cable ties (supplied)
POINT OF REFERENCE
The instructions provided in this manual assume the installer is standing behind the machine, looking toward the
machine cabin.