Installation
Check-out and Power-up
Node Controller Hardware User Manual 107
Rockwell Automation Publication MMI-UM013B-EN-P - April 2020
Check-out and Power-up
Node Controller Check-out
Before the node controllers are started for the first time, or after servicing, it is necessary to
check all operating and safety features.
The following startup procedure is used to apply power to the node controllers in an orderly
manner to make sure that they are in known conditions. This procedure is used to prepare the
node controllers for full operation.
Mechanical Checks
Make sure that the node controllers are properly and securely installed.
Make sure that all connections are secure.
If the optional E-stop circuit is being used, make sure that the button is functional.
Facility Checks
Make sure that all facilities meet, or exceed, the requirements as described in the Elec-
trical Specifications on page 64 and Site Requirements on page 83.
Make sure that the power and communications connections are complete.
Check all cables. Verify that the connectors are fully seated and screws/locks are
secured to make sure good continuity.
Verify that all cables are routed in a safe place and away from any travel areas.
Inspect all cables for restricting bend radii, excessive tension, or physical damage.