16.3.2.2 Configuring inrush current
For details of the configuration settings, see Chapter 16.3.2, "Inrush current",
on page 972.
1. Select "Analysis" > "Power".
2. Under "Input", select "Inrush Current".
3. Connect the current probe to the oscilloscope.
4. Select the correct channel for the "Current Source".
5. Select "Vertical" > "Probe Setup" > "Channel" and set your probe parameters.
6. Connect the probes to the DUT as shown in the "Channels" tab:
7. Select the "Settings" tab.
8. Set the "Trigger current value".
9. Set the "Maximum current" that should be displayed in the vertical scale.
10. In the "Gate configuration" table, define the different time periods. You can set up
to five different gates.
11. Tap "Execute".
12. Start the DUT.
On the screen, you can see the result box with the inrush current of each gate. For
details, see Chapter 16.3.2.1, "Inrush current results", on page 972.