Page - 95 -
FLF 15000/1800/500
Panther 8x8 CA-7
© 2014
Maintenance
Flushing after Foam Operation
ATTENTION !
To ensure the pump operates without malfunctions, it is important
to flush the pump, priming pump, pipes and foam proportioner.
Flushing with the internal flushing line - automatic flushing procedure
Whenever the pump is operated with clean water as mentioned in the
◊
"Air Crash Mode Operation" or
◊
"Tank Suction Operation" or
◊
"Drafting Operation from Open Water Source" chapter,
the pump system is flushed automatically.
- Shift pump system to manual mode:
◊
Press switch (S54), the integrated pilot lamp illuminates.
- Select the maximum proportioning rate:
◊
Press switch (S14/3), the integrated pilot lamp illuminates.
- Open all outlets (turrets, undertruck nozzles, hose reels, pres-
sure outlets).
- Increase pump pressure to approx. 5 bar.
- Carry on flushing until clean water is discharged.
- Open manometer flushing valves (J164) placed behind the
gauges on the left and right* hand sides.
- Before completion of flushing, flush the priming pump:
◊
Reduce pump speed to idle (pump pressure below 2 bar).
◊
Press switch (S3) for approx. 5 seconds.
- Disengage the pump engine:
◊
Please refer to the "Starting the Pump Engine" chapter.
- Drain the entire pump system:
◊
Please refer to the "Operation in Cold Climates" chapter.
8%
3%
S54
S14/3
S3
ATTENTION !
The Flushing procedure must be done carefully after each foam
operation, as well as after operation with seawater or mucky
water.
Drain the pump system when flushing is finished.
J164