7.6 ELECTRICAL SYSTEM CONNECTION
- Connect the runways cables on the electric main board connectors;
- Connect the feeding cable inside power unit;
- Ensure the grounding or earth is connected.
Figure 25 - ELECTRICAL SYSTEM CONNECTION
7.7 CONNECTION OF THE PNEUMATIC LINES
Warning: The connection of the lift to the general pneumatic system must be
carried out only when the platforms have been raised to the top position to
prevent mechanical safeties from disengaging unintentionally .
The disengagement of the gear racks and the locking of the slip plates are carried out pneumatically
(only for models AT e LTAT).
The pneumatic supply at site (to which the pneumatic system of the lift is connected) must be
equipped with a servicing unit composed of water separator, oiler and pressure reducer. These
devices can be supplied by the manufacturer on request
For the connection of the pneumatic lines proceed as follow:
Raise the lift to the final top position
Connect the pneumatic lines pre-assembled on the runways in the control desk according to
the color marking
Connect the pneumatic system of the lift to the pneumatic supply at site
Check the pneumatic control operations for proper performance