11. Installation
25
117592 ● 03/2013
Set up the columns vertically or slightly tilted
outwards with the help of a plumb line. If the
floor is not level, use the supplied shims under
the columns to align them.
The mounting holes with a diameter of 20 mm
are drilled with the help of a hammer drill. Use
the drill template in the column base plates as a
guide (Fig. 21). Please also refer to the adjacent
table and work instruction in Fig. 22.
21
Drill diameter 20 mm
Recommended concrete
thickness
200 mm
Drilling depth A 140 mm
Anchoring depth C 105 mm
Anchor bolt
Quantity min. 5 per column
Type M20 x 200/60
Tightening torque 200 Nm
Minimum distance to edge of
foundation slab
100 mm
If the required tightening torque cannot be
reached, either the hole is too large and the
thickness or the compression strength is too
low.
20
Short cable clamp
Cable clamp
Latch
Secondary column
ncho
Long cable clamp
Mounting plate
Primary
column
Cable clamp
Latch