1 - INSTALLATION AND COMMISSIONING
Installation and User Guide - N56717020101
No reproduction or communication without the written consent of
SAGEM SA
Page A1-19
Equipment Inventory
- 48 V power Check
Aggregate optical loopback
LOCAL TEST
Local Test on network
of last équipment ?
no
Link established
Optical measurements
MSP protection check
24 H link Performance
Counters reset
Equipment operational
(constitution of installation file)
Tributary Ports continuity check
A and B loops and alarms check
Local transmission test (30 mn) *
Optical connection
Connection of external sync input from of an "Master" equipment
(optional)
Configuration Elaboration
- 48 V redundancy Check
yes
Insertion of communication parameters (VT100)
Setting to time and insertion of the test configuration tributary accesses
(HTTP browser)
* case of underequipped
unitary equipment
Configuration Save
Figure 1-8 – Commissioning procedure for ADR155C network