Operating Manual Biowelder
®
Total Containment 17
Start-up
4. Start welding sequence
Check on the touch screen whether the type of tube entered matches with
the type of tube inserted. Check inside and outside diameter as well. If all
specifications match, press the start button to start the welding sequence.
The welding is finished when the cover opens.
Afterwards proceed as follows:
1. Remove blade with the blade remover tool
(ref to Chapter 5.8 Blade handling)
The blade cooling remains switched on until the blade is removed by the
user or the after-cooling time of two minutes have elapsed.
Each blade may only be used once.
2. Remove tubes from the holder
If the welding seam sticks together, pinch it gently to open up.
3. Check quality of welding
For an optimal connection, let the tube cool for about one minute before
checking the welding and before the thermal weld is mechanically loaded.
4. Dispose of waste tube appropriately
The welding is now finished and a new welding sequence can be started.

Table of Contents