Planning, transport, installation
LASERTEC 40
Page 3
Planning
What is the purpose of this documentation?
Basics
This documentation is aimed at the people responsible for installing the
machine and their staff. Contained in this documentation is all the
information necessary for the preparation of the machine's installation
location and its surroundings such that the machine can be installed
immediately on delivery. Information on the transport of the machine to the
place it is to be installed is also included.
Please also note the information on the tools and lubricants necessary.
Initial commissioning
The machine is only allowed to be initially commissioned by a person
authorised by the machine manufacturer. Otherwise, SAUER will accept
no liability whatsoever for any damage or malfunctions that may occur.
Effective utilisation of the machine
Training courses
SAUER provides training and further training for specialist personnel as a
service. Whether the machine’s features are actually utilised depends on
the user’s qualifications. For this reason, clarify in good time whether your
staff has the necessary knowledge. Plan your training course dates such
that all training measures are complete before the delivery of the machine.
Notes for your planning
Planning
The floor area mentioned in this documentation applies only to the
machines with the peripheral equipment as shown.
For information on the floor area and space required by the options you
have ordered, please refer to the related installation diagrams.
The machine documentation is applicable independent of the information
in this documentation.