Planning, transport, installation
LASERTEC 40
Page 6
Necessary preparatory measures
Actions to be undertaken by the customer
The customer is responsible for the following preparatory measures:
Installation location
• Preparation of installation location for the machine.
- See “Conditions for installation location”.
• Ensuring the availability of:
- Supply of electricity, light, water, telephone
Transport
• Organise the unloading of the machine.
• Transport within the factory to the installation location and installation
of the machine.
- The machine is to be transported to the installation location.
- The machine is to be placed on levelling elements.
E/P connection
• Connection of machine.
- The machine is to be connected electrically (clockwise rotating
field).
- The machine is not allowed to be connected to mains with a
residual current circuit breaker (fixed connection required).
- On delivery to countries with large voltage fluctuations on the
supply to the machine, a mains stabiliser must be used to protect
the electronic components.
- The machine is to be connected to the compressed air supply.
Placing in operation
• Preparation for commissioning
- Provide the necessary lubricating oils / cooling lubricants.
- Clean machine (de-grease).
- Align machine: ± 0,1 mm/m.
- Provide suitable assistants during commissioning.