14.2. MAINTENANCE
14.2.1. Keep parts clean and safety equipment in good working order.
14.2.2. Replace or clean all plates or stickers providing instructions for use and safety information.
14.3. VERIFICATION:
14.3.1. The statutory verications (provided for in the order of 21 December 2004) are broken down as follows:
14.3.2. Verication prior to the service launch on each installation site:
- prior to initial use,
- in the event of dismantling following by reassembly of the sca󰀨olding,
- following a change to the usage, atmospheric or environmental conditions which could a󰀨ect safety when using the sca󰀨olding,
- following an interruption in usage for at least one month.
14.3.3. This verication includes an examination of suitability, assembly and installation and an examination of the general condition of the
facilities. The traceability of this verication will be recorded in the establishment’s safety register.
14.4. DAILY VERIFICATION
14.4.1. This consists of examining the general condition of the facilities.
14.4.2. The traceability of this verication is recorded in a sheet provided on the access hatch.
14.5. QUARTERLY VERIFICATION
14.5.1. Since the scope of this verication in the case of mobile sca󰀨olding is comparable to that of the daily verication, a verication carried
out at least once every 3 months is recorded in the establishment’s safety register.
NOTE: These verications may only be carried out by members of sta󰀨 in possession of a certicate of competency issued by the head of the
establishment with the reference “Verier and User”.
15. DISMANTLING & FOLDING
15.1. PRIOR TO DISMANTLING:
15.1.1. Ensure that the sca󰀨olding is stable:
Brake wheels blocked.
Stabilisers correctly positioned, etc.
15.1.2. Use ropes to handle elements if necessary.
15.2. PRIOR TO HANDLING:
15.2.1. Replace the pins and stoppers on the elements concerned.
15.2.2. Isolate the damaged components to be replaced.
15.3. DURING DISMANTLING:
15.3.1. Follow the assembly procedure in the reverse order.
15.3.2. Follow the instructions below for the folding base:
g.32