103
8011952/YWL2/3-0/2016-08| SICK OPERATING INSTRUCTIONS | DUSTHUNTER C200
Subject to change without notice
MAINTENANCE 5
5.4 Shutdown
The measuring system must be shut down:
Immediately when the purge air supply fails
If the equipment is to be put out of operation for a longer period of time (as from approx.
1 week)
Work to be performed
Loosen the connection line to the MCU.
Dismantle the sender/receiver unit and reflector/scattered light receiver from the duct.
Close off the flange with tube with a blind plug.
Switch off the purge air supply
Loosen the hose clamps and pull the purge air hose off the connections and secure the
hose ends against dirt and moisture
Disconnect the MCU control unit from the supply voltage.
Storage
Store dismantled device parts in a clean, dry location.
Use suitable auxiliary means to protect the connection line plug connectors against dirt
and moisture.
Secure purge air hoses against penetration by dirt and moisture.
NOTICE:
Never switch off or interrupt the purge air supply when the sender/receiver unit and
reflector/scattered light receiver are fitted on the duct.
WARNING: Hazard through gas and hot parts
Observe the relevant safety regulations as well as the safety notices in Section 1
during all disassembly work.
Only remove the sender/receiver unit and reflector/scattered light receiver on
equipment with hazard potential (higher internal duct pressure, hot or aggressive
gases) when the equipment is at a standstill.
Take suitable protection measures against possible local hazards or hazards
arising from the equipment.
Secure switches that should not be switched on again for safety reasons with
signs and safeguards to prevent unintentional switching.