Figure 50: Control panel
1
Yellow
2
Red
3
Green
4
Alignment LED
Ö 3 Hz yellow
The yellow LED on the front and the Alignment LED on the control panel flash quickly.
►
Improve the alignment of the MLG-2.
✓
When the yellow LED and the Alignment LED go out, the MLG-2 is optimally aligned.
►
Now fix the position of the sender and receiver.
6)
Teach-in
►
Press the Teach pushbutton (<1s)
7)
✓
Ö 1Hz yellow
✓
The yellow LED on the front and the Alignment LED flash slowly.
If the teach-in process is successful, the yellow LED on the front and the Alignment LED
go out. The MLG-2 is operational.
If the teach-in process is unsuccessful, the Alignment LED flashes rapidly, as does the
red LED on the front of the device.
►
Check that the MLG-2 is correctly aligned, that the front screens are clean, and
that there are no objects located in the light path.
►
Then carry out the teach-in process again.
6)
You can also use the installation wizards in SOPAS ET to perform the alignment work (see "System boundaries and status", page 96).
7)
.Teach-in can also be triggered via SOPAS ET or the PLC.