Transport, storage and packing
10 9229 9992 176 0D
2013-07-08
• Set the vacuum circuit-breaker down onto the square timbers.
• Hang further sling gear into the transport boreholes.
• Transport to installation site or leave suspended from crane for further
work steps.
Fig. 8 Positioning the square timbers and setting
down the vacuum circuit-breaker
Fig. 9 Transporting without pallet
Note
Keep partitions and accessory pack ready for the installation.