Commissioning
3.3 Preparing the connection to the SINAMICS
Connection of the SINAMICS S120 to the Technology CPU
34 Product Information, 09/2011, A5E00480378-04
Result
The network configuration is now completed. Once again check the MPI address settings of
the PG/PC interface (address 0) and the Technology CPU (address 2) in the overview and
save and compile the network configuration.
Load the configuration into the target device.
The successful activation of the routing function is indicated by the connection of the
PG/PC interface with the MPI network having a yellow background in the overview.

Table of Contents

Other manuals for Siemens 6ES7 305-1BA80-0AA0

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 6ES7 305-1BA80-0AA0 and is the answer not in the manual?

Siemens 6ES7 305-1BA80-0AA0 Specifications

General IconGeneral
BrandSiemens
Model6ES7 305-1BA80-0AA0
CategoryController
LanguageEnglish

Related product manuals