Commissioning
4.5 Commissioning with STARTER
CU240S and CU240E Control Units, FW 3.2
Operating Instructions, 03/2009, A5E02440075B AA
59
4.5.1 Creating a STARTER project
Description
An inverter can be parameterized in a user-friendly fashion using the Project Wizard. The
commissioning procedure described here follows the Project Wizard. The PC communicates
with the inverter via the USS interface.
Switch on the inverter supply voltage
Launch the STARTER commissioning tool.
Use the Project Wizard and click on the "Find drive units online ..."
Figure 4-4 Start field
In the screen that follows (not shown here), enter a meaningful name into your project,
e.g. "Basic Commissioning" and click on "Continue". The following dialog box is
displayed.
Figure 4-5 Setting the PC interface
Click "Change and test..." to set up the PG/PC interface.