100 Start-up Protocol
MAMMOMAT Novation DR SPB7-250.815.06.02.02 Siemens AG
12.05 CS SD 24
Page 100 of 116
Medical Solutions
Work per-
formed
Yes No
Start-up:
Check power supply voltages ...........................................................
Mechanical checks performed ..........................................................
X-Ray tube checks performed ..........................................................
Collimator checks performed ............................................................
Dose settings checked ......................................................................
Acquisition workstation configurations performed .............................
Configured DICOM services .............................................................
Image quality tests performed ...........................................................
Acceptance tests performed ..............................................................
Ground wire tested .............................................................................
Line resistance tested ........................................................................
Backup for acquisition workstation and MAMMOMAT created............
SP Q "Quality Certificate" filled in and sent, when problems occurred