Siemens AG SPR8-230.831.30.03.02 MOBILETT XP Digital
11.05 CS SD 24
General maintenance information 27
Page 27 of 74
Medical Solutions
Document the measuring procedure (differential measurement or direct measurement)
and the measuring device used (designation and serial number).
In the case of repeat measurements, the measured value must also be evaluated.
NOTE
For evaluation purposes, the first measured value and the values
documented during maintenance or safety checks must be com-
pared to the measured values. A sudden or unexpected increase
in the measured values may indicate that a fault has occurred in
the primary power supply circuit (insulation damage, damage from
moisture, defective interference suppressor, etc.) - even if the limit
value of 2.5 mA is not exceeded.
The evaluation is not necessary in the case of a new determination.
NOTE
File the leakage current report in the "Certificates" register no. 9 in
the system binder.
NOTE
A new report must be created if the leakage current measurements
are not documented.
A new leakage current report can be found in the startup instruc-
tions SPR8-230.814.30.03. Separate this report from these instruc-
tions, fill it out, and file it in the "Certificates" register no. 9 in the
system binder. If values are newly determined, they must be re-
corded as first measured values. The evaluation is omitted in this
case.