2.3 Commissioning
To commission the controller:
Make certain that mounting and electrical installation are in compliance with the
relevant requirements
Make all plant-specific settings as described in section "Parameter settings"
Reset the attenuated outside temperature
Make the functional checks
2.3.1 Functional checks
To facilitate commissioning and fault tracing, the controller allows output and input tests
to be made. With these tests, the controller’s inputs and outputs can be checked.
Buttons Explanation Line
1 Press one of the line selection buttons.
This will take you to the programming mode.
2 Press both line selection buttons for at least 3
seconds.
This will take you to the programming mode “Heating
engineer” and, at the same time, to the output test.
3 Press the + or - button repeatedly, which will take you
one test step further:
Test step 0 All outputs are switched according to normal
control operation
Test step 1 All outputs are deactivated
Test step 2 Burner stage 1 (K4) is activated
Test step 3 Burner stages 1 and 2 (K4 + K5) are activated
Test step 4 D.h.w. charging pump / diverting valve (Q3 / Y3) is
activated
Test step 5 Mixing heating circuit / boiler pump (Q2) is
activated
Test step 6 Mixing valve OPEN (Y1) is activated
Test step 7 Mixing valve CLOSED (Y2) is activated
Test step 8 Multi-functional output (K6) is activated
Test step 9 Multi-functional output (K7) is activated
4 By pressing any of the operating mode or line
selection buttons, you leave the programming mode
and thus the output test.
Note:
If no button is pressed for about 8 minutes, the
controller will automatically return to the operating
mode selected last.