Connection
3.4 Installing the Control Unit
Frequency inverter
40 Operating Instructions, 08.10. 2008, t.b.d.
3.4 Installing the Control Unit
Locating the Control Unit on the power unit
The Control Unit is simply snapped-on to a Power Module. This also establishes all of the
electrical connections between the two components.
The Control Unit can be removed by pressing the release button ③.
Removing the terminal cover
To access the control terminals, remove the
cover as shown in the adjacent diagram.
Maximum cable cross-section for control
terminals, 2.5 mm
2
.
Tightening torque, 0.25 Nm

Table of Contents