Commissioning
4.5 Commissioning with STARTER
Frequency inverter
70 Operating Instructions, 08.10. 2008, t.b.d.
4.5.4 Commissioning the application
Description
You can now commission your application using the "Drive Navigator" screens or by
using the functions available in the project tree.
Save your settings so that they are protected against power failure (see below).
Once you have commissioned your application, disconnect the online connection
between the PC and converter by clicking on
.
Figure 4-16 Application communication
Saving data so that it is protected against power failure
In the project tree, select your SINAMICS project
Double-click on "Drive Navigator".
Select "Commissioning" in the working area
In the dialog box, select "Save data in the drive (RAM to ROM)".
You can now disconnect the online connection with