Connection system
6.4 Connecting-up information
1PH7 induction motors (Machine tools)
Configuration Manual, (APH7W), 04/2009, 6SN1197-0AD72-0BP0
217
After connecting-up, the following points should be checked/tested
The inside of the terminal box must be clean and free of any cable pieces
All of the terminal screws must be tight
The minimum air distances must be maintained
The cable glands must be reliably sealed
Unused cable glands must be closed and the plugs must be tightly screwed in place
All of the sealing surfaces must be in a perfect condition
Connecting the ground conductor
The ground conductor cross-section must be in full conformance with the installation
regulations, e.g. acc. to IEC/EN 60204-1.
For shaft height 225, the ground conductor must be additionally connected to the motor
bearing shield. There is a terminal lug for the ground cable at the designated connection
point. This is suitable for connecting multi-conductor cables with cable lugs or flat cables with
the appropriately prepared conductor end.
Please note the following when connecting-up:
The connecting surface must be bare and must be protected against corrosion using a
suitable medium, e.g. with acid-free Vaseline
There is a spring washer and normal washer underneath the screw head
The minimum necessary screw-in depth and the tightening torque for the clamping bolts
must be maintained
Table 6- 4 Screw-in depth and tightening torque
Screw Penetration depth: Tightening torque
M8 x 30 > 8 mm 20 Nm